ClientCardiff Netball Club
-
LocationMyall Road CARDIFF
-
Resurfacing of Netball Courts – Approx. 3740m2
SCOPE OF WORKS:
- Complete occupational safety requirements – including documentation
- Set up safety signage - as necessary
- Profile failed sections to a depth of 50mm on second court – Approx. 72m2
- Dispose of spoil to an approved waste disposal site
- Excavate to a depth of 200mm to area around tree on second court – Approx. 50m2
- Remove and dispose tree roots penetrating into court area – Approx. 50m2
- Supply and lay 200mm of stabilised road base to section near tree on second court – Approx. 50m2
- Roll & compact
- Sweep area clean of loose material
- Supply & spray tack coat of emulsion
- Supply & lay 50mm of asphaltic concrete (AC7) to failed sections on second court – Approx. 72m2
- Supply & lay 30mm of asphaltic concrete (AC7) to all court surfaces – Approx. 3740m2
- Lay surface with sonic metering to ensure level surface
- Roll & compact
- Clean & tidy area
All courts done together in one job
.