ClientGosford Public School
-
LocationGosford Public School
-
Area #2 – 2 x 25mm layers of AC10 & AC7 Wearing Course – Approx. 475m2
SCOPE OF WORKS:
- Area #2 – 2 x 25mm layers of AC10 & AC7 Wearing Course – Approx. 475m2
- Complete occupational safety requirements – including documentation
- Base preparation by others
- Sweep area clean of loose material
- Supply & spray tack coat of emulsion
- Supply & lay two layers of 25mm of asphaltic concrete (AC10 & AC7) – Approx. 475m2Roll & compact
- Additional handwork
- Clean & tidy area
Duration: 2 Days
.