accurate-asphalt-and-road-repairs-machinery-on-the-new-england-highway

RMS - New England Highway

  • Client
    Roads and Maritime Services
     
  • Location
    Murrurundi in New South Wales
  • The total area of work required to be stabilised
    Site 1 New England HWY at Liverpool Range 11,500m2
    Site 2 New England HWY at Kankool 29,300m2
     

Pavement Rehabilitation of two sections of the New England Highway near Murrurundi in New South Wales. Full service in-situ stabilisation of existing pavement material including pre-milling, spreading and incorporating additive, compaction and trimming to provide a heavily bound pavement of UCS > 4MPa, meeting the ride requirements of RMS R75.

SCOPE OF WORKS:

  • Full service in-situ stabilisation of existing pavement material including pre-milling, spreading and incorporating additive as nominated at the respective sites, compaction and trimming to provide a heavily bound pavement of UCS > 4MPa, meeting the ride requirements of RMS R75.
  • Final trimming including saw cutting centre lines and edge lines at 120mm depth 48hours after trimming, with pavement to be returned to existing levels and cross fall.
  • Removal of excess spoil associated with trimming.
  • Sealing of stabilised pavement in accordance with RMS R106.
  • Line marking in accordance with RMS R141 and R142.

 

.

Interested In Working With Us?

    (02) 4942 6100