ClientEnergised Alliance, North Sydney
-
LocationNewcastle sub-station to Merewether sub-station - feeder 770
-
Mill & Fill to 5km of Trenches - 50mm x ac14 to approx. 10,000m2
SCOPE OF WORKS:
-
Mill & Fill to 5km of Trenches - 50mm x ac14 to approx. 10,000m2
INCLUSIONS:
-
Complete occupational safety requirements – including documentation
-
Set up safety signage - as necessary
-
1.5 hours team induction
-
2 x establishments
-
Base is as per existing, no base preparation
-
Mill & profile to a depth of 50mm – approx. 10,000m2
-
Dispose of spoil to an approved waste disposal facility - haulage only with zero gate fee
-
Key in edges to ensure smooth transitions
-
Sweep area clean of loose material
-
Supply & spray tack coat of emulsion
-
Supply & lay 50mm of asphaltic concrete (AC14)
-
Roll & compact
-
Traffic control included
-
Clean & tidy area
Duration – Over a 4-6 Week Period to work within their schedule
.